Put The Acceptance Risk In The Smallest Milestone
When final acceptance happens on hardware you will never physically touch, that stage is the one you control least. On a fixed-price engagement, weighting milestones by effort puts your largest payment behind your weakest position. Weight them by controllability instead: the big work sits in the middle, where you own the bench, and the remote-acceptance stage is deliberately the smallest.